VTCU, CORP. OSHA Record
POCATELLO, Idaho · Manufacturing (NAICS 335311)
Inspections
4
Citations
78
Current penalties
$1,158,511
Penalties may change through settlement or contest. An open case is not final.
Inspections
Inspection 348301888
- Opened
- Jun 3, 2025
- Type
- Follow-up
- Case status
- Open
| Standard | Type | Issued | Initial penalty | Current penalty |
|---|---|---|---|---|
| 29 CFR 1910.178(l)(1)(i)Powered Industrial Trucks (Forklifts) | Serious | Dec 2, 2025 | $11,348 | $11,348 |
| 29 CFR 1910.178(p)(1)Powered Industrial Trucks (Forklifts) | Serious | Dec 2, 2025 | $11,348 | $11,348 |
| 29 CFR 1910.179(f)(2)(iii)Overhead & Gantry Cranes | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.179(f)(6)(iii)Overhead & Gantry Cranes | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.179(l)(3)(i)Overhead & Gantry Cranes | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.243(c)(1)Guarding of Portable Powered Tools | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.242(a)Hand & Portable Powered Tools | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.303(b)(8)(i)Electrical – General | Serious | Dec 2, 2025 | $8,512 | $8,512 |
| 29 CFR 1910.303(g)(2)(i)Electrical – General | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.305(b)(2)(i)Electrical – Wiring Methods & Components | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.305(b)(1)(i)Electrical – Wiring Methods & Components | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.334(a)(2)(ii)Electrical – Use of Equipment | Serious | Dec 2, 2025 | $11,348 | $11,348 |
| 29 CFR 1910.179(l)(3)(ii)(b)Overhead & Gantry Cranes | Repeat | Dec 2, 2025 | $99,300 | $99,300 |
| 29 CFR 1910.179(n)(4)(i)Overhead & Gantry Cranes | Repeat | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.179(l)(3)(ii)(d)Overhead & Gantry Cranes | Repeat | Dec 2, 2025 | $99,300 | $99,300 |
| 29 CFR 1910.179(l)(3)(iii)(c)Overhead & Gantry Cranes | Repeat | Dec 2, 2025 | $70,938 | $70,938 |
| 29 CFR 1910.254(d)(9)(iii)Arc Welding & Cutting | Repeat | Dec 2, 2025 | $70,938 | $70,938 |
| 29 CFR 1910.305(g)(2)(iii)Electrical – Wiring Methods & Components | Repeat | Dec 2, 2025 | $0 | $0 |
Inspection 348291782
- Opened
- Jun 3, 2025
- Type
- Follow-up
- Case status
- Open
| Standard | Type | Issued | Initial penalty | Current penalty |
|---|---|---|---|---|
| 29 CFR 1910.23(c)(8)Ladders | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.94(a)(3)(i)(e)(1)Ventilation | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.94(a)(4)(ii)Ventilation | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.94(a)(4)(iii)Ventilation | Serious | Dec 2, 2025 | $11,348 | $11,348 |
| 29 CFR 1910.94(a)(5)(v)Ventilation | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.132(d)(1)Personal Protective Equipment | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.133(a)(1)Eye & Face Protection | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.135(b)(1)Head Protection | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.138(b)Hand Protection | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.94(a)(6)Ventilation | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.107(b)(5)(i)Spray Finishing Using Flammable Materials | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.107(g)(2)Spray Finishing Using Flammable Materials | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.107(m)(1)Spray Finishing Using Flammable Materials | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.134(c)(1)(i)Respiratory Protection | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.134(c)(1)(vii)Respiratory Protection | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.134(c)(1)(ix)Respiratory Protection | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.134(k)Respiratory Protection | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.134(d)(1)(iii)Respiratory Protection | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.134(e)(1)Respiratory Protection | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.134(g)(1)(i)(a)Respiratory Protection | Serious | Dec 2, 2025 | $11,348 | $11,348 |
| 29 CFR 1910.134(h)(1)(ii)Respiratory Protection | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.134(h)(2)(i)Respiratory Protection | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.141(d)(1)Sanitation | Serious | Dec 2, 2025 | $14,188 | $14,188 |
| 29 CFR 1910.141(d)(2)(ii)Sanitation | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.212(a)(1)Machine Guarding | Serious | Dec 2, 2025 | $14,188 | $14,188 |
| 29 CFR 1910.212(a)(3)(ii)Machine Guarding | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.244(b)Other Portable Tools & Equipment | Serious | Dec 2, 2025 | $14,188 | $14,188 |
| 29 CFR 1910.253(b)(1)(ii)Oxygen-Fuel Gas Welding & Cutting | Serious | Dec 2, 2025 | $11,348 | $11,348 |
| 29 CFR 1910.253(b)(2)(iv)Oxygen-Fuel Gas Welding & Cutting | Serious | Dec 2, 2025 | $14,188 | $14,188 |
| 29 CFR 1910.253(b)(5)(ii)(i)Oxygen-Fuel Gas Welding & Cutting | Serious | Dec 2, 2025 | $14,188 | $14,188 |
| 29 CFR 1910.1200(e)(1)(i)Hazard Communication | Serious | Dec 2, 2025 | $16,550 | $16,550 |
| 29 CFR 1910.1200(h)(3)(ii)Hazard Communication | Serious | Dec 2, 2025 | $0 | $0 |
| 29 CFR 1910.28(b)(1)(i)Fall Protection | Repeat | Dec 2, 2025 | $99,300 | $99,300 |
| 29 CFR 1910.94(a)(3)(i)(a)Ventilation | Repeat | Dec 2, 2025 | $85,122 | $85,122 |
| 29 CFR 1910.94(a)(7)Ventilation | Repeat | Dec 2, 2025 | $0 | $0 |
Inspection 347540262
- Opened
- Jun 10, 2024
- Type
- Complaint
- Case status
- Closed
- Closed
- Apr 28, 2025
| Standard | Type | Issued | Initial penalty | Current penalty |
|---|---|---|---|---|
| 29 CFR 1910.23(c)(11)Ladders | Serious | Oct 23, 2024 | $7,604 | $5,703 |
| 29 CFR 1910.28(b)(1)(i)Fall Protection | Serious | Oct 23, 2024 | $10,140 | $7,605 |
| 29 CFR 1910.94(a)(3)(i)(a)Ventilation | Serious | Oct 23, 2024 | $12,676 | $9,507 |
| 29 CFR 1910.94(a)(7)Ventilation | Serious | Oct 23, 2024 | $0 | $0 |
| 29 CFR 1910.107(b)(5)(i)Spray Finishing Using Flammable Materials | Serious | Oct 23, 2024 | $15,211 | $11,408 |
| 29 CFR 1910.107(d)(2)Spray Finishing Using Flammable Materials | Serious | Oct 23, 2024 | $0 | $0 |
| 29 CFR 1910.107(g)(7)Spray Finishing Using Flammable Materials | Serious | Oct 23, 2024 | $7,604 | $5,703 |
Inspection 347440687
- Opened
- Apr 24, 2024
- Type
- Complaint
- Case status
- Closed
- Closed
- Sep 30, 2025
| Standard | Type | Issued | Initial penalty | Current penalty |
|---|---|---|---|---|
| General Duty Clause – 5(a)(1)General Duty Clause | Serious | Oct 23, 2024 | $16,131 | $12,098 |
| General Duty Clause – 5(a)(1)General Duty Clause | Serious | Oct 23, 2024 | $16,131 | $12,098 |
| 29 CFR 1910.179(j)(2)(iii)Overhead & Gantry Cranes | Serious | Oct 23, 2024 | $0 | $0 |
| 29 CFR 1910.28(b)(11)(ii)Fall Protection | Serious | Oct 23, 2024 | $7,604 | $5,703 |
| 29 CFR 1910.179(j)(3)Overhead & Gantry Cranes | Serious | Oct 23, 2024 | $16,131 | $12,098 |
| 29 CFR 1910.179(k)(2)Overhead & Gantry Cranes | Serious | Oct 23, 2024 | $16,131 | $12,098 |
| 29 CFR 1910.179(l)(3)(ii)(b)Overhead & Gantry Cranes | Serious | Oct 23, 2024 | $16,131 | $12,098 |
| 29 CFR 1910.179(l)(3)(ii)(d)Overhead & Gantry Cranes | Serious | Oct 23, 2024 | $16,131 | $12,098 |
| 29 CFR 1910.179(l)(3)(iii)(c)Overhead & Gantry Cranes | Serious | Oct 23, 2024 | $12,676 | $9,507 |
| 29 CFR 1910.179(l)(3)(iii)(d)Overhead & Gantry Cranes | Serious | Oct 23, 2024 | $0 | $0 |
| 29 CFR 1910.179(m)(1)Overhead & Gantry Cranes | Serious | Oct 23, 2024 | $16,131 | $12,098 |
| 29 CFR 1910.179(n)(4)(i)Overhead & Gantry Cranes | Serious | Oct 23, 2024 | $16,131 | $12,098 |
| 29 CFR 1910.184(e)(3)(ii)Slings | Serious | Oct 23, 2024 | $16,131 | $12,098 |
| 29 CFR 1910.184(d)Slings | Serious | Oct 23, 2024 | $0 | $0 |
| 29 CFR 1910.184(i)(9)(iii)Slings | Serious | Oct 23, 2024 | $0 | $0 |
| 29 CFR 1910.254(d)(9)(i)Arc Welding & Cutting | Serious | Oct 23, 2024 | $10,140 | $7,605 |
| 29 CFR 1910.254(d)(9)(iii)Arc Welding & Cutting | Serious | Oct 23, 2024 | $0 | $0 |
| 29 CFR 1910.305(g)(2)(iii)Electrical – Wiring Methods & Components | Serious | Oct 23, 2024 | $0 | $0 |
Other OSHA records in POCATELLO and Idaho
- KIA KAHA BUILDERS LLC
POCATELLO · Mar 23, 2026
$3,000
- LA QUINTA BY WYNDHAM
POCATELLO · Jan 21, 2026
$1,986
- BABA AGAND ENTERPRISES, LLC
POCATELLO · Dec 19, 2025
$2,251
- WORTH STEEL, LLC
POCATELLO · Mar 5, 2025
$3,784
- B G FRAMING LLC
POCATELLO · Jun 5, 2024
$11,845
- ROUGHNECK CONSTRUCTION, LLC
POCATELLO · Mar 14, 2024
$2,507
- CONSTRUCTION SOLUTIONS COMPANY, LLC
POCATELLO · Mar 12, 2024
$12,340
- GREENLEAF ROOFING SOLUTIONS LLC
MERIDIAN · Aug 18, 2026
$2,270
- BLUE SIDING LLC
MERIDIAN · Aug 18, 2026
$3,404
- JOHNSON BROTHERS HOSPITALITY, LLC
MOUNTAIN HOME · Aug 13, 2026
$3,376
More OSHA data
Get alerts when Idaho manufacturing companies are cited
Start free trialSource: U.S. Department of Labor public enforcement data, as of Oct 22, 2026. OSHAlert is not affiliated with OSHA.
Penalties may change through settlement or contest. An open case is not final.
See something wrong? Email support@oshalert.com.